Griffin Wind Farm |
Information & Updates for Griffin Wind Farm Please find the latest information and updates below: _________________________________________________________________________________________ |
GreenPower Enters Griffin Joint Venture [19th February 2009] GreenPower is pleased to announce that it has entered into a Joint Venture Agreement with Airtricity,
part of Scottish & Southern Energy plc, the Perth based energy utility, to construct and operate Griffin Wind Farm. _________________________________________________________________________________________ |
Update . . . . . Proposals for Access [17th December 2008] A822 works at Railway Bridge During November engineering exploratory works were carried out on the A822 near the railway bridge
at Ladywell, to enable engineering designs to create sufficient clearance for abnormal loads approaching the railway bridge.
It is expected that these design changes will involve lowering of the highway close to the bridge and some bank stabilisation
work either side of the bridge. When the engineering assessment is complete, we expect to submit a planning application
for approval of these works. Alternative access proposals As part of the access and transport assessment, GreenPower is also investigating an alternative route
for large loads to reach the eastern side of the wind farm site via the Craigvinean Forest. This alternative access would
leave the A9 directly at the existing "Whitegates" forestry haulage gate and would reach the Griffin wind farm site
predominantly along the route of existing timber haulage tracks. Project timeframe Works on the Griffin site itself are expected to commence in the Spring/Summer of 2009, subject to all necessary permits and subject to the contractor’s detailed construction programme. Broadly, however, the project programme is expected to roll out as planned with construction during the remainder of 2009 and throughout 2010, with turbine deliveries commencing in 2010 and finishing by the end of the year or early in 2011, approximately 22 months from the construction start date. _________________________________________________________________________________________ |
Update......Temporary Road Closure Now Over [29th October 2008] Temporary works on the A822 were completed on Tuesday 28th October. The temporary road
closure and diversions are no longer required and signs will be removed. _________________________________________________________________________________________ |
Update......Temporary Road Closure [17th October 2008] Temporary works on the A822 are now scheduled to take place on Monday 27th
and Tuesday 28th October and, in order to minimise any effect on school and commuter traffic,
the closure will be restricted to the period 09:30 to 15:00 each day. _________________________________________________________________________________________ |
Temporary Road Closure [9th October 2008] The Griffin project is proposing to design works to improve the road layout
and geometry in the vicinity of the railway over-bridge on the A822 (at the Dunkeld end, close to the A9).
Our engineers have written to Perth & Kinross Council to allow a road closure to facilitate
the investigation. Click on the thumbnail to see the location of the works. _________________________________________________________________________________________ |
| For further Information please contact GreenPower: _________________________________________________________________________________________ |